Statoil and the partners in the Åsgard Unit have decided to realise the Smørbukk South Extension project in the Norwegian Sea.
Smørbukk South Extension holds estimated recoverable reserves of 16.5 million barrels of oil equivalent, and will be developed with a new subsea template connected to existing infrastructure in the area.
The recovered gas will be reinjected in the reservoir in order to maintain the reservoir pressure as oil is drained out. The field will be connected to the Åsgard A installation (FPSO).
"We've matured a profitable project out of a discovery from 1985. Experience from Åsgard operations, existing infrastructure and a bit of patience have contributed to an investment decision for this project.
"In addition we will consider the use of a new well technology that will increase the recovery from this type of reservoir. Smørbukk South Extension is a strategically important project that emphasises our ambitions to increase recovery from mature areas," says Astrid Helga Jørgenvåg, Statoil's asset owner for Åsgard.
The Smørbukk South Extension project development will be based on standard equipment. Pre-investments have been carried out in order to minimise the time from project sanction to production start-up.
Statoil will now award several contracts for the development. Nexans was awarded the umbillical contract last year.
Drilling operations are planned to start in early 2015, and production start-up is planned for September 2015. The lifetime of Smørbukk South Extension is estimated to be 12 years.
"With the investment decision for Smørbukk South Extension, another piece in the puzzle is now in place for the development of the Åsgard field. The project will contribute to the prolonged lifetime on Åsgard A and will facilitate the development of other projects and prospects in the area," says Ola Gussiås, Statoil's project manager for the Smørbukk South Extension project.
The total investments are estimated to be about NOK 3.5 billion.
(NRK/Press release)




The National Congress of Prime Minister Jens Stoltenberg's Labour Party has voted yes to do a study that examines the effects of potential oil drilling in the Lofoten-Vesterålen area in the north of Norway.
..
Norwegian engineering firm Aker Solutions has entered a frame agreement with Petrobras to provide subsea equipment for the oil company's deepwater pre-salt field developments in Brazil.
..
Final investments in oil and gas activity in 2012 - including pipeline transportation - were NOK 172.5 billion; 18 per cent higher than in 2011. The forecast for 2013 has been adjusted downwards to NOK 198.7 billion, according to Statistics Norway.
..
This week, Statoil and its partners began production from the Hyme oil field in the southern part of the Norwegian Sea. Hyme is the second of Statoil’s 12 so-called fast-track projects.
..